The Port of Charleston’s busiest terminal was built in 1982 to handle ships in the 2,000- to 4,000-TEU range, but now regularly accepts vessels with capacities for 5,000 to 8,000 TEUs. In the future, it is expected to receive vessels of more than 13,000 TEUs.
The port authority in its application asked for $20 million. The modernization project is estimated to cost more than $85 million, Port Director Jim Newsome said.
Improvements include strengthening the wharf piling structure to support bigger, heavier ship-to-shore cranes and withstand pressure from of the largest vessels; paving; replacing gantry rails with wider gauge tracks to support two new super post-Panamax cranes on order; modifying wheel surfaces on existing cranes to fit in the new tracks, and other repairs.
SCPA is investing about $30 million more for the cranes, which are scheduled to be placed in service in July 2016, according to spokeswoman Erin Dhand. Two smaller cranes will be relocated from Wando to the North Charleston Terminal, which cannot be reached by the largest vessels because a downriver bridge has air-draft restrictions.
The port authority board recently approved $1.7 million in modifications to the new cranes that will raise their height under the spreader bar to 155 feet.
Construction work is expected to start early next year and continue for more than two years, Newsome told reporters following his state-of-the-port address on Sept. 8.
At certain points in construction one of the three berths will have to be temporarily closed, he said.
This article was published in the November 2014 issue of American Shipper.
Brokerage Compliance Symposium
The day before F3. Every compliance issue you face - fraud exposure, carrier liability, FMCSA rules, cargo theft, insurance gaps - navigated by attorneys and operators defining best practices in a changing industry.
F3 Awards Dinner
The night before F3. FreightTech100 companies honored. FreightTech 25 and Shipper of Choice winners revealed live. Cocktail reception into dinner and live music - 300 industry leaders in one purpose-built room.
F3: Future of Freight Festival
Industry-defining keynotes, rapid-fire technology demos, and industry leaders networking in experiences across Chattanooga - plus the inaugural F3 Awards Dinner featuring the FreightTech and Shipper of Choice reveals.
The day before F3. Every compliance issue you face - fraud exposure, carrier liability, FMCSA rules, cargo theft, insurance gaps - navigated by attorneys and operators defining best practices in a changing industry.
The Signal at Chattanooga Choo Choo • Chattanooga, TN Register NowThe night before F3. FreightTech100 companies honored. FreightTech 25 and Shipper of Choice winners revealed live. Cocktail reception into dinner and live music - 300 industry leaders in one purpose-built room.
The Signal at Chattanooga Choo Choo • Chattanooga, TN Register NowIndustry-defining keynotes, rapid-fire technology demos, and industry leaders networking in experiences across Chattanooga - plus the inaugural F3 Awards Dinner featuring the FreightTech and Shipper of Choice reveals.
The Signal at Chattanooga Choo Choo • Chattanooga, TN Register Now