It means construction can resume on the first phase of the terminal, which could eventually grow to 1,043 acres, with seven containership berths, an intermodal rail yard, and an industrial development area.
The terminal is being built to accommodate growing trade arriving via the Gulf of Mexico, with Houston's key Barbours Cut container terminal limited by space constraints.
The Bayport terminal project has come under fire from some community groups and local municipalities who contend that the Corps’ improperly delineated wetlands to be preserved, among other allegations. In exchange for building the terminal, the port said it has designed the terminal to minimize the effects of construction on the surrounding area, and has preserved approximately 1,100 acres of land for environmental mitigation.
Officials at the port also say Bayport will fuel the creation of thousands of new jobs and will add hundreds of millions of dollars to the region’s economy.
In January 2004, the Port of Houston Authority and the Corps granted the federal permit for construction of the Bayport project, marking a critical step in the process to build the $1.2 billion terminal. Construction of Phase 1A — including 1,660 feet of the ultimate 7,000-foot wharf and approximately 65 acres of the ultimate 1,043 acre facility — began in June 2004 and is targeted for completion in summer 2006. Additional phases are planned to be built incrementally on an as-needed basis.
Brokerage Compliance Symposium
The day before F3. Every compliance issue you face - fraud exposure, carrier liability, FMCSA rules, cargo theft, insurance gaps - navigated by attorneys and operators defining best practices in a changing industry.
F3 Awards Dinner
The night before F3. FreightTech100 companies honored. FreightTech 25 and Shipper of Choice winners revealed live. Cocktail reception into dinner and live music - 300 industry leaders in one purpose-built room.
F3: Future of Freight Festival
Industry-defining keynotes, rapid-fire technology demos, and industry leaders networking in experiences across Chattanooga - plus the inaugural F3 Awards Dinner featuring the FreightTech and Shipper of Choice reveals.
The day before F3. Every compliance issue you face - fraud exposure, carrier liability, FMCSA rules, cargo theft, insurance gaps - navigated by attorneys and operators defining best practices in a changing industry.
The Signal at Chattanooga Choo Choo • Chattanooga, TN Register NowThe night before F3. FreightTech100 companies honored. FreightTech 25 and Shipper of Choice winners revealed live. Cocktail reception into dinner and live music - 300 industry leaders in one purpose-built room.
The Signal at Chattanooga Choo Choo • Chattanooga, TN Register NowIndustry-defining keynotes, rapid-fire technology demos, and industry leaders networking in experiences across Chattanooga - plus the inaugural F3 Awards Dinner featuring the FreightTech and Shipper of Choice reveals.
The Signal at Chattanooga Choo Choo • Chattanooga, TN Register Now